Winterrevisionsplan 2017 / 2018

LockChamberFromToAdditional info
Ybbs-PersenbeugRight chamberFeb 2018March 2018Repair of mitre gate
AltenwörthLeft chamber7.11.201730.3.2018NfB 95/00; Repair works